Iraq International Airport Project
Project Name: Iraq International Airport New Construction Project
Commissioning Time: June 2025
Project Nature: A key national aviation hub rebuilt after the war, designed for an annual passenger flow of 750,000
Core Requirements: Provide a stable, reliable, and weather-resistant power distribution system for the entire 4E-level international airport.
Core Equipment: TSTY Electric's customized medium-voltage switchgear, prefabricated substations, and transformer solutions.
Project Significance: Iraq's first post-war airport infrastructure project, and the largest aviation hub in the southern region.

Technical Highlights and Equipment Performance
- Extreme Environment Adaptability Design: All outdoor equipment (such as prefabricated substations) adopts a fully enclosed, high-protection-level (IP65 or higher) design, effectively preventing sand and dust intrusion and ensuring stable operation of internal components in high-temperature environments above 50℃.
- Key conductive components and casings are coated with special anti-corrosion and UV-resistant coatings, adapting to high-salt and alkaline air environments and ensuring long-term equipment service life.
- High Reliability and Intelligent Protection: Provides a dual-power automatic switching scheme for primary loads such as airport runway navigation lights, terminal buildings, and air traffic control systems, ensuring zero power interruption.
- High- and low-voltage switchgear is equipped with high-precision digital protection devices, achieving millisecond-level fault isolation and protecting the airport's core power grid.
- An integrated intelligent online monitoring system allows for remote monitoring of equipment temperature, partial discharge, mechanical characteristics, and other statuses, enabling predictive maintenance.
- Seismic resistance and rapid deployment capabilities:
The equipment structure is designed with seismic resistance to withstand a certain level of geological vibration, meeting regional safety standards.
Modular and prefabricated design significantly reduces on-site installation and commissioning time, meeting the requirements of rapid delivery for overseas projects.
Project Benefits and Data Demonstration
1. Reliability Record: All power distribution equipment provided for the airport's 3400-meter runway, 18,000-square-meter main terminal building, and air traffic control system has achieved "zero-failure" operation since commissioning, ensuring the airport's timely opening.
2. Environmental Tolerance: During sustained summer temperatures exceeding 50°C and severe sandstorms, all outdoor equipment operating parameters remained normal, with no protective actions triggered due to excessive temperature rise or sandstorms.
3. Energy saving effect: By adopting low-loss transformers and high-efficiency reactive power compensation devices, it is expected to reduce the airport's overall line loss electricity costs by 5%-8% annually.